Initiative Timeline for Jira
Keep one list of initiatives with start and end dates, attach the Jira
issues that belong to each one by issue key, and see the initiatives as lanes on
a single timeline, each with a % done figure read from Jira.
Where to find it after installing
The app is a global page. Open Apps in Jira’s sidebar and choose
Initiative Timeline. There is nothing to configure first.
Adding an initiative
At the bottom of the page, under New initiative:
- Enter a Name. It is required, and can be up to 120 characters.
- Optionally enter a Start date and an End date, written as
YYYY-MM-DD (for example 2026-10-01).
- In Issue keys, enter the keys of the Jira issues that belong to this
initiative, separated by commas, spaces or new lines. One initiative can link
up to 100 keys.
- Click Add initiative.
Before you save, the form tells you what it made of the keys you entered, for
example: “2 valid key(s) recognised. 1 duplicate(s) collapsed: KAN-3. 1
entry/entries are not issue keys and will be ignored: not-a-key.” Keys are
upper-cased, so kan-3 and KAN-3 count as the same key.
After a save the page confirms it, for example “Added “Mobile app relaunch”. 4
issue key(s) linked.”, and the form empties.
The app never finds issues for you. It reads only the keys you enter.
Nothing is saved, and the form says why, when:
- the name is empty: “Name is required.”
- the name is longer than 120 characters: “Name is 121 characters; the limit
is 120.”
- a date is not a real date in
YYYY-MM-DD form: “Start date “01/10/2026” is
not a real date. Use YYYY-MM-DD, for example 2026-01-31.”
- the end date is before the start date: “End date 2026-05-01 is before the
start date 2026-06-01.”
- there are more than 100 issue keys. The form warns you before you click, and
the save is refused with a message that names the keys beyond the limit. The
app does not quietly keep the first 100.
Reading the page
The list sentence at the top says how many initiatives are shown, for
example “Showing all 5 initiatives.”
The timeline has one lane per initiative. Each lane is positioned and sized
by that initiative’s own dates, against the span of all the dated initiatives,
which the caption states: “Timeline spans 2026-01-12 to 2026-12-18 (341 days),
across 5 dated initiatives.” The bars show dates, not progress.
- An initiative with only a start date or only an end date is drawn as a single
day.
- An initiative with no dates is not drawn. The caption says so, for example
“1 initiative has no dates and is listed below the chart instead of drawn on
it.”
% done appears under each lane and on each initiative’s card, for example
“0% done — 0 of 2 linked issue(s) are in a Done status category.” It is the
share of the linked issues that Jira returned whose status is in Jira’s Done
status category. It is a count of issues, not of story points or hours.
Keys that Jira did not return are named on the card and left out of the
percentage, rather than counted as not done:
“1 of 3: KAN-58. They may have been deleted, moved, or be invisible to you.”
A key that does not exist is reported this way.
The issue status line under the timeline says how many of the linked keys
Jira returned, for example “Issue status: 15 of 16 distinct linked key(s)
returned by Jira, over 1 query and 1 page(s).”
Show issues on a card opens a table of that initiative’s issues with the
columns Issue, Summary, Status and Done?.
Editing and deleting
- Edit on a card loads that initiative into the form. Change it and click
Save changes. The page confirms it, for example “Saved “Mobile app
relaunch”. 4 issue key(s) linked.”
- Delete on a card asks you to confirm first, then removes the initiative
and says “Initiative deleted.” No Jira issue is touched. A deleted
initiative cannot be recovered.
Permissions
The app asks for two Atlassian permissions:
- read:jira-work, to read the status and summary of the issue keys you
attach;
- storage:app, to store your initiatives.
The app never creates, edits, transitions or deletes anything in Jira.
Limits and known issues
- For a moment after the page loads, and after you add an initiative, the page
can wrongly say that linked issues did not come back from Jira. The issues
have not been deleted. The page corrects itself once Jira’s answer arrives.
- When we loaded the page, every card with linked issues briefly said “No
progress can be shown: none of the … linked issue(s) came back from Jira”,
and the issue status line read “0 of 0”. About a second later both were
correct.
- After adding an initiative whose issues were not already on the page, the
new card said none of its issues came back. In our measurements it was
corrected within about three seconds of clicking Add initiative.
- What to do: wait until the issue status line shows the number of keys
Jira returned, or reload the page. This page will be updated when a fix is
released.
- Typing very quickly into the Name field can occasionally drop a
character. With keystrokes 80 milliseconds apart, characters were lost in 2
of 12 attempts. With keystrokes 150 milliseconds apart, none were lost in 11
attempts. Check the name before you click Add initiative. You can correct a
saved name with Edit.
- The page shows at most 200 initiatives. If there are more, the page says
how many it showed and how many exist, for example “Showing the first 200 of
208 initiatives. 8 more were not loaded.”
- One initiative links at most 100 issue keys, and a name is at most 120
characters. Longer input is refused, not trimmed.
- No automatic discovery. The app does not find issues by epic, parent,
label, project or JQL. Only the keys you enter are read.
- Not a scheduling tool. There are no dependencies, no drag-and-drop (dates
are typed), no automatic scheduling, no sprints and no capacity planning.
- One list per Jira site. There are no per-project or per-person lists, and
no way to restrict who can see or edit an initiative.
- Two edits of the same initiative at the same time: the last save wins,
and the page that saved first is not told. Saves to different initiatives do
not affect each other.
- No history and no undo.
- No export and no notifications. Nothing runs unless someone has the page
open.
- Long unbroken text contains invisible characters. So that a very long
word cannot push the page sideways, the app inserts an invisible zero-width
space (U+200B) every 24 characters into unbroken runs longer than that, on the
cards, in the issue table, in the key-box messages and in the delete
confirmation. Nothing is removed. But text copied off the page carries those
characters, so paste it into a plain-text editor before using it as an issue
key or identifier. On the timeline itself a name with a very long unbroken run
scrolls sideways inside its label instead.
- Jira Cloud only. There is no Server or Data Center version.
Your data
The app runs entirely on Atlassian Forge.
- What is stored. Your initiatives are stored in Forge hosted storage for
your site’s installation. Each initiative record holds:
- its name, dates and linked issue keys;
- when it was created and last updated;
- the Atlassian account IDs of the people who created it and last updated
it.
- Account IDs are never sent to the page. Issue summaries and statuses are read
from Jira each time the page loads.
- Egress. The app makes no outbound network calls.
See the privacy policy for the
full detail.